*** NEWS: Road Closures On Picadome Park And Vista Street **

From the Division of Water Quality :

LEXINGTON, KY. (Aug. 22, 2025)  Beginning Monday, Aug. 25, Vista Street between Rosemont Garden and Picadome Park will be closed to all thru traffic. This is in addition to the recent closure of Picadome Park between Lafayette Parkway and Vista Drive.

These closures are due to sanitary sewer construction. They are expected to last for approximately one month. Residents will be able to access their homes during construction.

Drivers should use Lafayette Parkway, Reed Lane, Pin Oak Drive and Rosemont Garden to detour around the closures.

This work is part of a project to upsize approximately 4500 feet of sanitary sewer line along Wolf Run Creek. Construction is estimated to be finished by the end of 2026. This project is part of the federal consent decree requirements for Lexington to improve its sanitary sewer system.  

If you have any questions, you can reach out to following contacts:

10th District Council Office Office: 859-280-8263 Cell: 859-694-0535 lexingtonky.gov

Bob Peterson Division of Water Quality Office: (859) 425-2400 Email: rpeterson@lexingtonky.gov

ATTACHED MAP

Stay Informed: Wolf Run Watershed Plans & Meeting Info

Save the date!
Wednesday, March 5 at 6:30 PM. This meeting will cover plans and construction updates for the Wolf Run G Watershed, which runs through the Southland area. Construction is set to begin in Spring/Summer 2025. This is a great opportunity to stay informed and ask any questions. We hope you can join us! You can learn more about Lexington’s watersheds here

As Columbia Gas is completing the replacement of gas lines, we are reposting the information regarding the project :

Southbend Drive Closure – Wolf Run Sewer Project Trunk F

https://www.lexingtonky.gov/council-district-10#wolf-run-trunk-f-sewer-replacement

This project will replace and upsize over 3,500 feet of sanitary sewer line along Wolf Run Creek from Spring Meadows Drive to Lafayette Parkway.

  • Primary excavation approaching Clays Mill Rd and contractors are working to bore under Southbend Dr.
    • Little to no impact is expected on Clays Mill traffic.
    • Significant traffic impacts expected on Southbend Drive beginning around the second week of June.
    • The Southbend closure is expected to last through the end of July.
    • Lafayette Parkway traffic impacts are to be expected in late July and August.
  • Completion of the project is scheduled for the fall of 2024.

https://www.lexingtonky.gov/council-district-10#wolf-run-trunk-f-sewer-replacement

  • Replace and upsize 4,500 feet of sewer from Lafayette Parkway to Southland Drive.
  • Expect Significant traffic impacts on Picadome Park, Vista Street, Rosemont Garden and Cherry Bark.
  • Late summer/early fall.

For more information visit https://www.lexingtonky.gov/council-district-10#wolf-run-trunk-f-sewer-replacement